10.28.2021 - Updated 04.26.2024
|
Lawyer Publications
The table below focuses on filings by RTO/ISOs of changes to their tariffs and does not include any RTO/ISO filings that relate to a single entity or service agreement (e.g. filing of an interconnection agreement or change to an individual transmission owner rate), informational filings, or pleadings in response to the filings of third parties. Once the comment period for a particular filing has passed, the filing will be removed from this tracker for efficient viewing.
Click on the RTO / ISO below to see current RTO / ISO FERC Tariff Change Filings and Petitions
Filing Date and Docket |
Description |
Comment Deadline |
April 16, 2024 |
PJM proposed revisions to the PJM Open Access Transmission Tariff and the Amended and Restated Operating Agreement of PJM to effectuate a fundamental redesign of PJM’s Regulation market. As proposed, PJM’s Regulation market will shift from a market with one product and two signals (RegA and RegD) to a market with one signal and two products Regulation-Up (RegUp) and Regulation-Down (RegDown). PJM requested Commission action on the filing by June 16, 2024. Requested effective dates: “Phase 1” effective October 1, 2025, and “Phase 2” effective October 1, 2026. |
May 7, 2024 |
April 22, 2024 |
PJM submitted proposed re-dated eTariff records of the PJM Open Access Transmission Tariff, the Amended and Restated Operating Agreement of PJM, and the Reliability Assurance Agreement Among Load-Serving Entities in the PJM Region (RAA) applicable to the capacity market components of PJM’s Order 2222 compliance filing in Docket No. ER22-962. Specifically, PJM proposed to red-ate these eTariff records from their current effective dates July 1, 2023 and July 1, 2024 to a new effective date of July 1, 2025. PJM also proposed to modify a single textual reference in the definition of “DER Capacity Aggregation Resource” to align with the proposed change in effective date to July 1, 2025. Requested effective date: July 1, 2025 |
May 13, 2024 |
Back to top > | ||
N/A |
N/A |
N/A |
|
|
|
N/A |
N/A |
N/A |
|
|
|
April 17, 2024 |
SPP submitted revisions to Attachment AE of SPP’s Open Access Transmission Tariff to implement congestion hedging improvements. SPP’s filing is the result of the HITT M1 initiative, which sought to holistically examine congestion rights allocations and the cash flows therein to help equitably allocate congestion revenue. SPP seeks to improve the equity and fairness of access to congestion rights and surplus auction revenues to Eligible Entities. Requested effective date: 12/31/9998 (not known at the time of filing) |
May 8, 2024 |
|
|
|
N/A |
N/A |
N/A |
|
|
|
April 12, 2024 |
CAISO submitted a tariff amendment to implement the Extended Day-Ahead Market (EDAM) access charge. The EDAM tariff provisions previously accepted by the Commission extend access to the CAISO’s day-ahead market to balancing areas across the Western United States. To avoid unintended cost shifts from beneficiaries of broader participation in EDAM to existing customers of an EDAM transmission service provider, CAISO proposes the EDAM access charge to provide EDAM transmission service providers an opportunity to recover transmission revenues comparable to their historical cost recovery prior to their participation in EDAM. Requested effective date: May 1, 2026 |
May 3, 2024 |
April 25, 2024
|
CAISO submitted a tariff amendment to remove language in the CAISO tariff that states non-generator resources with resource adequacy capacity have a requirement to submit $0/MW availability bids in the residual unit commitment (RUC) process. CAISO explains this language is not consistent with the CAISO’s current practices, which do not support the submission of RUC availability bids by non-generator resources. Requested effective date: June 25, 2024 |
May 16, 2024 |
|
|
|
N/A |
N/A |
N/A |
|
|